| PROJECT HIGHLIGHTS |
| |
PERLIS
COMBINED CYCLE POWER PLANT, MALAYSIA
|
|
|
Perlis
Power Plant View |
Lifting
Stack Section into position for Heat
Recovery Steam Generator |
| |
|
- Mechanical and Electrical Erection
Works for a 675MW 3X KA 13E2 Perlis Combined
Cycle Power Plant.
- Mechanical and Electrical
Erection Works for 675MW 3X KA 13E2 Gas
Turbines, Steam Turbine, Balance of
Plant and Piping for Perlis Combined
Cycle Power Plant.
- Construction started in Feb 2002
and ended in Nov 2002.
- Client: Alstom Power Asia Pacific
Sdn Bhd
- Peak manpower: 800
|
|
Erection
of High Pressure Live Steam System
on Pipe Rack |
| |
| |
|
|
|