| PROJECT HIGHLIGHTS |
| |
SENOKO
POWER STATION, SINGAPORE
|
|
|
Diffuser I & II in position
|
Installation of lower
half air intake manifold
|
| |
|
- Mechanical Erection of 1 x 250 MW
ABB GT 26 Gas Turbines and associated
auxiliaries and piping works at Senoko
Power Station, Singapore.
- Electrical Installation
of 1
x 250 MW ABB GT 26 Gas Turbines, 1
x 120 MW rehabilitated Steam Turbine
and associated systems at Senoko Power
Station, Singapore.
- Supply of Manpower for Commissioning
work in Senoko Power Plant, Singapore.
- Supply of Manpower for Modification
Work of 1 x 250 MW Alstom GT26 in Senoko
Power Station, Singapore.
- Construction started and ended
in the year 2000
- Client: Alstom Power Asia Pacific Sdn
Bhd
- Peak manpower: 220
|
|
Gas Turbine horning
in progress
|
|
| |
|
|
|